abstract concepts > premature closure

Preferred term

premature closure  

Type

  • CHT concept

Broader concept

Scope note

  • The PRINCE2 activity to close a project before its planned closure. The Project Manager must ensure that work in progress is not simply abandoned, but that the project salvages any value created to date, and checks that any gaps left by the cancellation of the project are raised to corporate or programme management.